Abbott Ireland, Co. Monaghan

Where:

Dromore West, Cootehill,
Co. Monaghan.

What:

Fit Out & Ancillary Works

Duration:

January 2023 – June 2023

McCabe Group is very pleased to have completed upgrade works to this existing warehouse facility with works including:

  • Erection of cold store panels to enclose plant areas.
  • Construction of new mezzanine store area.
  • Extension of catwalk.
  • M&E upgrades.
  • Installation on new AHU.
  • Pest proof works to perimeter of warehouse and new floor finishes throughout.
  • Replacement of exisitng flat roof assembly to front of house and warehouse to include the stripping out and removal of the existing flat roof sheeting down to deck level.
  • Temporary propping of plant situated on roof and installation of new SIKA Warm Roof System including increasing height upstands to perimeter